NFPA 110 Generator Testing Requirements: Weekly, Monthly, Annual and 36-Month Tests Explained

By Djordje Milivojevic, Electrical Engineer · Updated · 7 min read

Short answer

NFPA 110 requires emergency generators to be inspected weekly and run under load for at least 30 minutes every month, at 30% of nameplate kW or the manufacturer's minimum exhaust temperature. Diesel units that cannot reach that load need an annual load bank test (50% for 30 minutes, then 75% for 60 minutes). Level 1 systems are also tested every 36 months, transfer switches monthly, fuel yearly, and every test is recorded.

In this article
  1. What is NFPA 110?
  2. What do Level, Type and Class mean?
  3. What testing and maintenance does NFPA 110 require?
  4. How does the monthly generator test work?
  5. When is an annual load bank test required?
  6. What is the 36-month test for Level 1 systems?
  7. What about transfer switches, batteries and fuel?
  8. What records does NFPA 110 require?
  9. How to stay NFPA 110 compliant across many sites
  10. Frequently asked questions
  11. Sources

NFPA 110, the Standard for Emergency and Standby Power Systems, is the reference most often used for how emergency generators should be installed, tested and maintained. It is written for the United States, but many operators elsewhere use its testing rules as the benchmark for standby power at critical sites.

This guide explains what the standard asks for in practice, from the weekly walk-around to the 36-month test, and how to keep the records that prove it was done.

Enclosed diesel standby generator installed next to the base of a lattice towerGenerator controller display in AUTO mode showing Ready
From our field operations: a standby generator at a critical site (left) and its controller in AUTO, ready to start on a utility failure (right). NFPA 110 is about proving, every week and every month, that it will.

What is NFPA 110?

NFPA 110 covers the performance of emergency power supply systems (EPSS): the generator, the transfer switches, the controls and everything between the power source and the load terminals. The current edition is 2025.

The standard itself does not decide which buildings need emergency power. Other codes do that, for example NFPA 101 (Life Safety Code), NFPA 99 for health care facilities and the electrical code articles on emergency and legally required standby systems. Those codes point to NFPA 110 for how the system must perform and be maintained. The authority having jurisdiction (AHJ), usually the local fire or building authority, enforces it.

What do Level, Type and Class mean?

Every EPSS under NFPA 110 is classified by three things:

TermWhat it definesValues
LevelHow critical the load isLevel 1: failure could cause loss of life or serious injury. Level 2: failure is less critical to life and safety
TypeMaximum time to restore power after an outageType 10 (10 seconds), Type 60, Type 120, Type M (manual), Type O (no interruption)
ClassMinimum time the system must run without refuellingClass 0.083 (5 minutes), 0.25, 2, 6, 48 hours, or Class X (other)

A hospital's life safety branch, for example, is typically Level 1, Type 10. The Class depends on the fuel the site must hold on hand.

Reading an NFPA 110 classificationExample classification Level 1, Type 10, Class 48: Level describes how critical the load is, Type the maximum time to restore power, Class the minimum run time without refuelling.Example: an EPSS classified Level 1, Type 10, Class 48Level 1How critical the load isFailure could cost livesor cause serious injuryType 10Time to restore powerLoad back on within10 seconds of the outageClass 48Run time without refuellingAt least 48 hourson the fuel kept on site
Three parts of every NFPA 110 classification. Level decides how strict the maintenance rules are, Type how fast the system must react, Class how much fuel the site must keep.

What testing and maintenance does NFPA 110 require?

Chapter 8 sets the routine. The main items:

IntervalRequirement
WeeklyInspect the EPSS: fuel, oil, coolant, battery and charger, leaks, alarms and general condition
MonthlyRun the generator under load for at least 30 minutes, at not less than 30% of nameplate kW or at a load that keeps the manufacturer's minimum exhaust gas temperature
MonthlyOperate the automatic transfer switches
AnnuallyLoad bank test for diesel units that cannot meet the monthly load: 50% of nameplate kW for 30 minutes, then 75% for 60 minutes
AnnuallyTest the fuel quality using ASTM methods
Every 36 monthsLevel 1 systems: run for the duration of the assigned Class, up to 4 hours
Every testKeep a written record of inspections, tests, exercising, operation and repairs

Manufacturers' maintenance schedules come on top of this. NFPA 110 asks for maintenance in line with the manufacturer's recommendations, so the oil, filter, coolant and belt intervals in the generator manual are part of compliance too.

NFPA 110 testing and inspection intervalsWeekly inspection, monthly load test and monthly transfer switch operation, annual load bank test where the monthly load is too low, annual fuel quality test, and a 36-month test for Level 1 systems, on a logarithmic time scale.The NFPA 110 calendar for one generatorTime between tests, logarithmic scale1 wk1 mo3 mo6 mo1 yr3 yrWeekly inspectionall systemsWeekly inspection: all systemsMonthly load test30 min, 30% kWMonthly load test: 30 min, 30% kWTransfer switch operationmonthlyTransfer switch operation: monthlyAnnual load bank testif monthly load is lowAnnual load bank test: if monthly load is lowFuel quality testASTM methodsFuel quality test: ASTM methods36-month testLevel 1 only36-month test: Level 1 onlyrequired intervalonly when the monthly test cannot reach the required load
The routine tasks in NFPA 110 chapter 8, plus the written record after every one. The manufacturer's own service intervals come on top.

How does the monthly generator test work?

The monthly test is the backbone of NFPA 110 compliance. Done properly, it tests the whole chain, not only the engine:

  1. Start it by simulating a utility failure at the transfer switch, so the start signal, the transfer and the retransfer are tested too.
  2. Run under load for at least 30 minutes, at 30% of nameplate kW or more, or at a load that reaches the manufacturer's minimum exhaust temperature.
  3. Record voltage, frequency, load, coolant temperature, oil pressure and any alarms.
  4. Let the load return to the utility and the generator run its cool-down before it stops.
  5. Confirm the generator controller and the transfer switch are back in automatic mode.
Monthly generator test sequenceSix steps: grid loss signal, engine start, transfer, run under load for at least 30 minutes at 30 percent or more, retransfer, cool-down and logging.1Grid losssignalswitch or ATS2Engine start10 s for Type 103Transferload to generator4Run underload30+ min, 30%+ kW5Retransferload to grid6Cool-downlog readingsMonthly test: exercise the whole chain, not only the engine
Starting the test from the transfer switch proves every link that has to work in a real outage. Start time limits depend on the system type; Type 10 systems must carry load within 10 seconds.

When is an annual load bank test required?

When a diesel generator cannot meet the monthly requirement with the building's own load, NFPA 110 requires it to be exercised monthly with the load that is available and, once a year, with a supplemental load: in practice a load bank. The minimum profile is 50% of nameplate kW for 30 minutes followed by 75% for 60 minutes, without stopping.

For how the test is run and which readings to record, see our guide to generator load bank testing.

NFPA 110 annual load bank test profileLoad held at 50 percent of nameplate kilowatts for 30 minutes, then at 75 percent for 60 minutes, total 90 minutes. Monthly test minimum shown at 30 percent.0%25%50%75%100%0 min15 min30 min45 min60 min75 min90 minMonthly test minimum: 30%50% for 30 min75% for 60 minStart at 50%Step to 75%End: 1.5 h total% of nameplate kW
The annual load bank minimum in NFPA 110 for diesel units that cannot reach 30% load or the manufacturer's exhaust temperature in monthly tests.

What is the 36-month test for Level 1 systems?

Level 1 systems are tested at least once every 36 months, running continuously for the duration of their assigned Class. Where the Class is longer than 4 hours, the test may end after 4 hours. The test is done with the building load available at the time; where that is too low, a load bank brings the load up. It is the closest thing to a real long outage the system will see on a planned day.

What about transfer switches, batteries and fuel?

  • Transfer switches are operated monthly, normally as part of the monthly generator test. Our ATS testing and maintenance guide covers the annual inspection.
  • Starting batteries are inspected weekly and maintained as the manufacturer specifies. Battery problems are one of the most common reasons a standby generator fails to start.
  • Fuel is tested at least once a year using ASTM methods, and the supply must be kept at the level the system's Class requires. See diesel fuel management.
Generator alternator terminal box with labelled power cables and voltage regulatorControl cabinet with scorch marks next to a terminal block
From our field operations: generator power terminals (left) and heat damage next to a terminal block in a site cabinet (right). Connections that carry load are where problems show first, which is why they are checked under load every year.

What records does NFPA 110 require?

A written record of every inspection, test, exercise, operation and repair must be kept on the premises and available to the AHJ. In practice a good record shows:

  • date, time and who did the work;
  • how the test was started and how long the transfer took;
  • load in kW and as a percentage of nameplate, and run time under load;
  • voltage, frequency, coolant temperature and oil pressure;
  • alarms, findings and what was done about them.

Paper logs work, but they are where compliance usually breaks: missing months, readings filled in afterwards, no load recorded. Readings taken from the controller and stored automatically leave a record nobody has to reconstruct before an inspection.

How to stay NFPA 110 compliant across many sites

  1. Know the Level, Type and Class of every system, and keep it on the site record.
  2. Schedule by rule, not memory: weekly, monthly, annual and 36-month tasks generated automatically for each generator.
  3. Measure the load of every monthly test, so the units that need an annual load bank test are known in advance.
  4. Capture readings from the controller and a digital checklist, with photos, on the day.
  5. Turn every failed check into a work order, and close it only when the fix is verified.

Frequently asked questions

How often does NFPA 110 require generator testing?

NFPA 110 requires a weekly inspection and a monthly test under load of at least 30 minutes. Diesel units that cannot reach the monthly load need an annual load bank test, and Level 1 systems need a test at least every 36 months. Transfer switches are operated monthly and fuel is tested yearly.

What is the NFPA 110 monthly load requirement?

The generator must run for at least 30 minutes either at not less than 30% of its nameplate kW rating, or at a load that keeps the exhaust gas temperature at the minimum recommended by the manufacturer.

What is the difference between Level 1 and Level 2 under NFPA 110?

Level 1 systems serve loads where a power failure could result in loss of human life or serious injury, such as life safety systems in hospitals. Level 2 systems serve loads that are less critical to human life and safety. Level 1 systems have stricter requirements, including the 36-month test.

What does Type 10 mean in NFPA 110?

Type 10 means the emergency power system must restore power to the load within 10 seconds of a utility failure. The time includes detecting the failure, starting the engine and transferring the load.

Does NFPA 110 apply outside the United States?

NFPA 110 is a US standard adopted through US codes and enforced by local authorities there. Outside the US it is not law unless a local code or contract adopts it, but many operators, insurers and contracts use its testing rules as the reference for standby generators.

Sources

  • NFPA 110, Standard for Emergency and Standby Power Systems, 2025 edition, chapters 4 (classification), 7 (installation and acceptance testing) and 8 (routine maintenance and operational testing).
  • NFPA 101, Life Safety Code, and NFPA 99, Health Care Facilities Code, which reference NFPA 110.
  • ISO 8528, Reciprocating internal combustion engine driven alternating current generating sets, for generator set performance outside the NFPA framework.
  • Related reading: generator load bank testing, generator maintenance schedule and checklist and ATS testing and maintenance.

See every generator's status and service plan in one place

GenSetCare reads alarms, fuel and run hours from the controller, schedules service by run hours and calendar, and gives technicians a field app with live checklists.